SKV40, Biomass, Denmark

Skærbækværket / Skaerbaek Power Plant 2 x 154 MW Biomass-Fired Boilers

Babcock & Wilcox Vølund (B&W Vølund) designed, manufactured and commissioned two biomass boilers for the Skærbækværket power plant in Denmark.
The project allows the combined heating and power plant to supply approximately 60,000 households  with clean and reliable district heating and electicity while reducing CO2 emissions.

SKV40 Biomass plant

Plant description

The Skaerbaek Power Plant (SKV40) is owned and operated by Ørsted A/S (formerly DONG Energy Thermal Power A/S).
Built in 1951, the plant originally used coal as fuel. In 1997, it was converted to gas before the conversion to wood chips in 2014. The wood chips are sourced from sustainable forestry and help to reduce the plant’s carbon emissions.

Biomass as sustainable fuel for district heating

B&W Vølund supplied two identical 154 MW wood chipfueled boilers, built on the harbor area in front of block 2 of the Skaerbaek plant. From the two boilers, a new steam pipe was established to the existing turbine of block 3 through which the boilers can supply steam for combined production of electricity and heat. The boilers are connected to a new heat exchanger for producing district heating independently of block 3’s operations.
Skærbækværket supplies about two-thirds of district heating to the municipalities in the triangle area that includes Fredericia, Kolding, Middelfart and Vejle. TVIS, the district heating company in the triangle area, invested in the conversion of the Skaerbaek Power Plant to biomass with the goal of making district heating cheaper, greener and more sustainable, and 100% CO2-neutral and independent of fossil fuels by 2050. The conversion to biomass is intended to reduce Skaerbaek’s CO2 emissions from district heating by approximately 83%. This is a reduction of 79,000 tonnes of CO2 each year.

Designed for flexibility and performance

The plant’s boilers were designed for maximum flexibility and performance. The boilers can utilize different fuels, and energy production can be controlled from a 25 to 100% load, depending on actual heat consumption or electricity prices. This allows the plant to maintain high availability when demand is high or adjusted in summer months when demand is lower. To ensure the most efficient utilization of wet fuel, energy in the flue gas is captured in a condensing unit before the gas exits through the plant’s stack. With this solution, the boilers are integrated into the existing plant and provide the highest degree of flexibility. Production output can be adapted to the district heating needs and market situation in the electricity market.

B&W Vølund's scope of supply - Biomass SKV40